Hi.
I have 8 unison tasks scheduled via the I-bay synchronisation plug-in module. They all involve the same 2 SME boxes. 7 of them are working reliably.
One of these synchronisations fails to complete at its scheduled time. When I choose the manual option "synchronise now", the message log (in the sending computer) shows the task constructing a list of changes, and this list just stops halfway through a line. So again, the task begins, but fails to complete.
I have tried creating a 9th task using the same source and destination i-bays, but this fails in the same manner.
Anyone recognise this symptom?
Many thanks.
David
-
I should add that yesterday I could manually complete the task when there were only a few updated entries.
However, after doing quite a lot of directory re-organising & file moving (perhaps 50 objects changed), the Unison task would not complete.
Is there perhaps a log file size limit when Unison is constructing its "to do" list?
Thanks